S&S Greenway Phase 3 Project (Federal Aid) & Josh Hagin Road Paving Project · Bonds
What this bid asks for in bonds.
From the documents Bulloch County Board Of Commissioners posted, in its own words, with the page.
-
Proposal guaranty
5%
Required
AMOUNT OF PROPOSAL GUARANTY: A bid bond in the amount of 5% of the total bid is required to be submitted with the bid.
FY27_ENGCP_002_1_S_SGreenwayPh3_JoshHaginRdPa.pdf, page 2 · copied Oct 17, 2026
-
Performance bond
100%
Required
… required to furnish a performance bond in the amount of 100% of the contract and a payment bond in the amount of 110% of the …
FY27_ENGCP_002_1_S_SGreenwayPh3_JoshHaginRdPa.pdf, page 2 · copied Oct 17, 2026
-
Payment bond
110%
Required
… the contract and a payment bond in the amount of 110% of the contract.
FY27_ENGCP_002_1_S_SGreenwayPh3_JoshHaginRdPa.pdf, page 2 · copied Oct 17, 2026
These are the agency's own sentences, found in the documents it posted. A bond not named here may still be required: read the documents, and ask the agency if they don't say. The agency's posting